Click on the Vendor Data Module to open the Vendor Data Register. The default view shows a hierarchical view of Contracts, Items Purchased and Deliverable Line Items.
Use the arrow buttons to the left of a contract to view the Items Purchased relating to the contract.
Use the arrow button next to an Item Purchased to view the Deliverable Line Item(s).
Use the arrow button next to a Deliverable Line Item to view the Documents associated with the item.
Deliverable Line Items are colour coded in the register:
Red indicates that there are documents that are overdue based on the Date Due and has nothing linked.
Green indicates that all linked documents are considered Unrestrained or Released.
No Colour indicates that no documents have been linked to the Deliverable Line Item.
Blue indicates that the received documents are currently under review, or resubmittal is required.
Additional Information