When the project planning and estimating are complete and the project is ready for execution, you can create your Original Budget and Current Budget from the project's plan data in the CBS. Rather than being stored in separate registers, this budget data is represented by columns right in the CBS.
When the project is released for execution, the following sets of budget data are all equal:
After the project has been released for execution, the Original Budget is locked. The only way to change the Current Budget or add a Pay Item is to add a Change Record in the Budget / Contract Changes Register.
If you remove the Original Budget and Current Budget, all contract changes will be moved into the Current Estimate. The Current Budget will then be merged into the Current Estimate. Any existing Budget / Contract Change Records will be deleted.