Change Records created automatically have a status of Pending and they will not be reflected in the project's Current Budget until the status has been changed to Approved.
To create Change Records automatically by capturing the differences between the Current Estimate and the Current Budget, use the following step-by-step below.
Change Records for parent level cost items can only be created for Quantity Changes. These records can be created automatically when Quantity changes already made to the current estimate is the only option selected, Man-Hour and Cost cannot be selected.
If none of the three check boxes are selected, all cost items that meet any of the criteria will be included.
Additional Information