Update Schedule Impact on Issue

A man wearing personal protective equipment uses a cell phone and laptop at a construction site
Use Case

The superintendent estimates the schedule impact for the issue based on information received so far from the client and notifies the scheduler.


On the issue record in InEight Change, you can detail the issue’s impact on the schedule. The system can then notify the scheduler automatically, and the scheduler can make note of the issue in the risk register in InEight Schedule.

Update Schedule Impact in InEight Change

When a change is requested or proposed in a project, it can have ripple effects on various tasks, activities, and milestones. These changes may involve altering the sequence of tasks, adjusting resource allocation, or revising the duration of certain activities. The schedule impact is the assessment of how these changes will influence the project's overall timeline.

The following steps walk through how to update the issue with schedule impact information:

Step 1

Open an existing issue, and in the Schedule Impact section, update if work has started and if it impacts the schedule.

A screenshot of a computer

Description automatically generated

Step 2

Add your current estimate of how many days this issue will delay the schedule.

Step 3

Add comments as needed.

A screenshot of a computer

Description automatically generated


Notify Scheduler of Issues

This notification in InEight Change is designed to alert relevant roles or individuals about potential issues that could impact the project schedule. the notification can be configured to trigger specific days, times, and occurrences. When the "YES" option is chosen, the Scheduler will receive an alert indicating an issue. The configured setup ensures that the receiver will receive the notification every day as specified.

The following steps identify how to set up scheduler notifications at the user or role level, so they receive a daily email notification anytime there’s a schedule impact.

Step 1

To set up notifications, go to Project Settings > Change > Notifications.

A screenshot of a computer

Description automatically generated

Step 2

Click on the Notify scheduler of issues tab, and toggle on the switch to send notification email to recipients when there are schedule impact changes.

A screenshot of a computer

Description automatically generated

Step 3

Assign roles/users as the recipients.

A screenshot of a computer

Description automatically generated

Step 4

Select a specific time for notifications to send, and click Save.

A screenshot of a computer

Description automatically generated

Step 5

Back on the issue record’s Details tab, an email is triggered when this setting in Schedule Impact is set to Yes.

A screenshot of a computer

Description automatically generated



Add Issue to Risk Register in InEight Schedule

Once the scheduler is notified of an issue, he or she can add it to the Risk Register in InEight Schedule so the Scheduling team can keep tabs on it as well.

Step 1

Within InEight Schedule, open the schedule the issue is related to.

Step 2

Select Risk Register from the View menu.

Step 3

Select the Add icon.

Step 4

On the resulting Add register event window, select Issue for the type of threat.

Step 5

Add a title and description, then click Add. 

Because this event’s type is Issue, when doing risk simulations, it will always calculate the issue as 100% probability (since it already happened). 

Access the following links to learn more:

Risk Register View


Back to Evaluate Schedule Impacts Main Page