Create an Issue from a vendor change order
Use Case
The client responds to an RFI indicating the contractor will need 100 additional tons of steel from their steel supplier for a scope change. As the superintendent creates a vendor change order for this, he also documents an issue so they can get paid by the owner.
When creating a vendor change order in InEight Contract, you can create a new issue from the VCO record and associate it to the VCO.
Create an Issue in InEight Contract
The following steps walk you through creating a new issue in InEight Contract.
Step 4
Create a new issue by clicking on the Add issue icon under Associated Change Items and selecting Add new issue. The issue shows up in the New Issue register of Change, with a pending status.
You may be creating this VCO after the issue was created or escalated to a potential change order (PCO). If that is the case, you can select Add existing change item.
Access the following links to learn more:
Vendor Change Orders topic