There are circumstances that warrant the transition of a piece of equipment to a different Preservation Plan.
The Project Admin needs to reconcile between the previous and new plans to ensure continuity in the maintenance. For example, if a piece of equipment is changed from Energized to Laydown, Warehouse, the frequency changes and needs to be reconciled.
For another example, the equipment is moving from a 3-month to a 6-month frequency cadence. If the activity for the first month was completed under the previous plan, then the new plan date needs to reflect a completed date 5 months out. The old plan is then abandoned.
Additional Information