Work Packages Overview Page

The Work packages Overview page provides transparency of various work package related items. You can open a work package overview page by clicking an Engineering or Deliverable work package in Scope Items > Actions > Configure work packages.

The table below is an overview of the Work and Deliverable work package overview page:

Overview - Work package overview page
 
Title
Description
1 Overview of test package

View and edit the current work package attributes.

2 % Complete % complete is based on the scope item hours and earned progress on scope items within the work package. ((Earned Qty x CE MHRs ÷ Unit) ÷ CE Hours).
3 Hours
  • CE – Sum of the scope item man hours for all scope items within a package (Scope Item Qty x CE MHRs ÷ Unit).

  • Earned – Sum of the scope item earned hours for all scope items within a package (Earned Qty x CE MHRs ÷ Unit).

  • Remaining – Sum of the scope item forecast remaining man hours for all scope items within a package (CE Hours – Earned Hours) if Control integration is off and ((Scope Item Qty – Earned Qty) x CE MHRs ÷ Unit) if Control integration is on.

4 Dates Start dates show the earliest date, and finish date will show the latest date from the related scope items.
5 Milestones

When the Project Settings – Dates setting is configured with Scope Item/Milestone, the milestones window will show. You can use the Dates Chooser icon to toggle between the following dates:

  • Planned start/finish

  • Current start/finish

  • Actual start/finish

  • Completion

6 Remaining steps View non-completed steps and their percent complete for all related scope items to the package. Remaining steps will be shown ascending based on step order.
7 Teams Shows all teams associated to the work package and the teams’ percent complete. The teams’ percent complete is based on scope item hours and earned progress the team is assigned to on the scope items within the work package (Earned Hours ÷ Scope Item Hours). An unassigned team will show for scope items that does not have a team assigned.
8 Gantt

List of scope items with their related work packages. In the Gantt chart, you can view the start and finish dates for the scope items within the work package. You can use the Dates Chooser icon to toggle between the following dates:

  • Planned start/finish

  • Current start/finish

  • Actual start/finish

When the Project Settings, Dates setting is configured with Scope Item/Milestone, you can expand the scope items and view the milestone dates below the scope item.

In the scope item list, when you click on a scope item link, the Edit scope item slide-out panel opens. You can view and make changes to scope items. When changes are saved, the overview page is updated to reflect the new changes.

Considerations

You must have the applicable permissions in Engineering.