InEight Model allows visual work packaging to support an Advanced Work Packaging (AWP), Work Face Planning (WFP), or any other work scoping process.
Work Packaging breaks down projects into small, manageable scopes of work so that operation can be assigned to responsible supervision, executed, and tracked effectively. Within InEight, our approach is to break the work of your project into Construction Work Areas (CWAs), Construction Work Packages (CWPs), and Installation Work Packages (IWPs).
AWP activities span the entire project. Front-end planning and detailed engineering activities support enhanced execution at the work front. Project set-up and planning sessions establish the basis for coordinated construction, procurement, and engineering work packages (CWPs, PWPs, and EWPs).
AWP drives the WFP concepts to Engineering and Procurement. Drawings are issued to construction and vendors as complete Engineering Work Packages (EWP) and Procurement Work Packages (PWP) instead of individual drawing releases. The objective is to ensure all parties follow the project Path of Construction.
To access the AWP Panel, select View from the menu bar at the top of the screen, and then select AWP.
This opens the AWP Panel.
• AWP Panel will display Work Packaging structure items (CWA, CWP, IWP) created in InEight Model, InEight Plan, or InEight Schedule applications
• Name: Work Package unique name or code
• Description: Brief work package description
• Start: Schedule start date
• Finish: Schedule finish date
• % Complete: Percent complete (earned work-hour basis)
• Platform: Identifies which platform (Model, Plan, Schedule) created work package structure item
• Add: provides the ability to:
Add CWA
Add CWP
Add IWP
Remove Item
• Settings: provides the ability to:
Toggle on/off the Auto-select material components feature
Visually select model objects that are assigned to work package structure
Toggle on/off the Show % complete feature
Activates progress visualization mode
Toggle on/off the Compact Mode feature
Reduces AWP panel down to only show CWA/CWP/IWP names
Toggle on/off the Edit RUID feature
Opens the AWP panel column customization widget
Additional Information