Creating & Managing CWA, CWP & IWP

The InEight platform allows users to generate AWP structure components (Construction Work Areas (CWAs), Construction Work Packages (CWPs), and Installation Work Packages (IWPs)) within Schedule, Plan, and Model. InEight’s cloud-based platform allows real-time synchronization between the solutions.

Adding to the existing AWP structure or creating a new structure to reflect the current project status is available in the Model.

Create a Construction Work Area (CWA)

  1. Select Add.

  2. Click Add CWA.

  3. Fill out the CWA ID (project unique code or identifier).

  4. Click OK, then the new CWA will display within the AWP panel.

    The platform name highlights which of the InEight solutions generated the CWA. Any CWA created in InEight Plan or Schedule will be available within Model.

Create a Construction Work Package (CWP)

  1. Select an existing CWP item, then Select Add.

  2. Click Add AWP.

  3. Fill out the CWP ID (project unique code or identifier).

  4. Click OK, then the new CWP will display within the AWP panel.

    The platform name highlights which of the InEight solutions generated the CWP. Any CWP created in InEight Plan or Schedule will be available within Model. With the InEight platform, additional metadata associated with the CWP will be visible within the InEight Model. Connecting AWP structure with InEight Schedule allows for schedule metadata to be visible within the InEight Model. Connecting AWP with InEight Plan & Progress allows for work-hours, progress percent complete, and other metadata to be visible within the InEight Model.

Create a Installatoin Work Package (IWP)

  1. Select an existing CWP item, then Select Add.

  2. Click Add IWP.

  3. Fill out the IWP ID (project unique code or identifier).

  4. Click OK, then the new IWP will display within the AWP panel.

    The platform name highlights which of the InEight solutions generated the IWP. Any IWP created in InEight Plan or Schedule will be available within Model. With the InEight platform, additional metadata associated with the CWP will be visible within the InEight Model. Connecting AWP structure with InEight Schedule allows for schedule metadata to be visible within the InEight Model. Connecting AWP with InEight Plan & Progress allows for work-hours, progress percent complete, and other metadata to be visible within the InEight Model.

Deleting AWP Structure

  1. Select one or multiple AWP structure items.

    Removing AWP structure items (CWA / CWP / IWP) must happen at the lowest level of the structure first. If an IWP has elements associated with it, these elements must be unlinked before deleting. The same logic applies to CWPs and CWAs.

  2. Right mouse click on the AWP structure items, then select Remove IWP (or Remove CWP, or Remove CWA).

Filter AWP Structure

Filter the AWP structure per predefined criteria

Select one or multiple AWP structure items.

  1. Select the Filter tab, then set the criteria as desired.

    Additional filters can be added as desired.