You can perform claiming in the AWP panel’s Claiming tab, and then sync with InEight Plan. You can mark the completion of claiming schemes in full or enter a partial install quantity.
You can perform bulk and individual claiming at the CWP and IWP level by tapping the Claim icon.
You can also perform partial and full claiming by tapping individual steps and entering the install quantity or select Yes in the Is Complete field.
When you perform claim updates, the updates are saved to your Project Updates queue, and then when you perform a sync operation, the updates for claiming sync with Plan. You must perform a sync operation to sync your updates to Plan.
Reverse claiming must be done in the Plan application. After you reverse claiming quantities in Plan, changes will sync in Model.