You can perform claiming in the Elements panel’s Claiming tab and sync with InEight Plan. You can mark the completion of claiming schemes in full or enter a partial install quantity.
The following image shows claiming in the Elements panel:
Complete quantity claiming – Select a component in the Elements panel, click the Components claiming icon, and then select the Edit component icon. Mark the claiming item’s checkbox to do complete claiming.
Partial and complete quantity claiming – To do partial claiming, select a component in the Elements panel, click the Components claiming icon, and then select the Edit component icon. Tap on an item, tap Install Quantity, enter a quantity, and then click Ok.
You can also do full claiming by selecting Yes in the Is Complete field.
When you do claim updates, the updates save to your Project Updates queue. When you sync, updates for claiming sync with Plan. You must perform a sync operation to sync your updates to Plan.
Reverse claiming must be done in the Plan application. After you reverse claiming quantities in Plan, changes will sync in Model.
Additional Information