Schedule 24.3 Release Notes

View Options

  • Hide No Results - In View Options, the Hide No Results toggle has been added that lets you hide WBS items that do not return any results. ClosedRead more

    The new Hide No Results toggle lets you hide any WBS groupings on the Plan page that do not yield any results.

    For more information, see Hide No Results.

Project Risk Register

  • Project Register Matrix number ranges - The number of ranges in the Project Register Matrix has been increased from seven to nine so you can see additional attributes available for events, and the values available when entering data for an event. ClosedRead more

    For more information, see Risk Register View.

  • Project Matrix Opportunity Color scale - The Opportunity Color column was added in the Project Register Matrix, which shows a blue scale to help differentiate various opportunities. The Opportunity Color scheme shows throughout the application where opportunities are presented. ClosedRead more

For example, in the Project Register Events page, the Opportunity in the second row shows three different color ranges that are associated with the Opportunity Description in the Project Register Matrix.

The Opportunity ranges one through nine (Ultra High to Ultra Low) and the blue color scale is also visible in the Mitigation page for opportunities.

For more information, see Risk Register View.

  • Risk Register Schedule import - The Schedule Microsoft Excel import format has been updated to accept new Risk Register ranges. ClosedRead more

    For more information, see Risk Register View.

Plan

  • Float Paths - In the Schedule Plan settings, you can now calculate up to 10 sub-critical paths. ClosedRead more

    This helps you to better envision the activities that have a potential of being delayed, which gives you additional time and consideration to push out the schedule. You can choose to execute certain actions such as defining the critical activities by using either free float or total float, select an activity to stop showing multiple float paths, and determine the number of float paths to calculate.

    To see the float paths in plan , you can group by float path in the Group By Builder to see which activities are critical and sub-critical, and the float path where they reside.

    For more information, see Scheduling.