Video - InEight Schedule
Assigning Project Events

TRANSCRIPT

Welcome to InEight Schedule. This video demonstrates how to add threats,

opportunities, issues, et cetera to the Schedule W B S Elements.

Risk Register events can be added to any level of the schedule.

When the register column is included in the schedule view,

you'll see a number indicating existing register items.

To view an existing register event,

select the number icon in the register column.

You'll see existing register events in the project register folder on the iris

panel, on the right hand side of the screen.

Select any level of the project to create a new project register event.

Select add event.

InEight Schedule will first present a folder to add new register event.

View an existing register event being used on the schedule item,

or select a suggested register event.

Just like smart planning InEight Schedule uses the context of the current WBS

element to suggest applicable register events in the Smart Suggestions tab.

You can also select from register events that already exist in the current

project from the project tab

and look at all the register events that exist in the Knowledge Library Master

Register.

You can select from existing register events by simply clicking on one.

The register event has been added to your project.

If the register event is a risk or opportunity,

the default score will be included. You can change the score as you see fit.

You can also add a new risk or other risk events to the project in

the Add New register event folder, select the type of event you want to add.

Give the element a title and a description and select add.

The register events will now be part of your project.

You can modify the score of a register event and also delete an event in the

project register.

Well, that's how to add events in InEight Schedule.

Thanks for watching.