Reorder Project Summaries

TRANSCRIPT

Welcome to InEight schedule. This video demonstrates how to rearrange and regroup WBS elements and work packages. First, what is a WBS and a work package? A WBS is an element of the hierarchy that does not directly contain activities, pre-construction, procurement and construction are examples.

A work package is an element in the hierarchy that has activities. Design and permitting are examples. You can grab and rearrange these elements and all their children very quickly. You can also move and regroup elements easily.

Rearranging and regrouping WBS and work packages is persistent for a project and all users that have access to that project. These actions do not affect how the project is scheduled or the dates of activities. It only affects how the project is organized. Well, that's how to rearrange and regroup WBS elements and work packages.

Thanks for watching.