For cost items you create in InEight Estimate, you need to add resources, assemblies and production to define their costs. In this exercise, you will practice defining cost details. Complete the following steps, using your job:
|
Code |
Description |
Quantity |
|---|---|---|
|
LO1 |
Operator Class 1 |
1 |
|
LL2 |
Laborer |
2 |
|
LL3 |
Labor Foreman |
1 |
|
EX225 |
Excavator 225 |
1 |
|
CY/Hour |
400 |
|
|
Code |
Description |
Quantity |
|---|---|---|
|
LO1 |
Operator Class 1 |
1 |
|
LL2 |
Laborer |
2 |
|
LL3 |
Labor Foreman |
1 |
|
LT1 |
Teamster |
1 |
|
EL950 |
Loader 950 |
1 |
|
ETDT |
Dump Truck |
1 |
|
EX225 |
Excavator 225 |
1 |
| CY/Hour | 400 |
|
Code |
Description |
Quantity |
|---|---|---|
|
MPP10 |
Pipe 10” PVC SDR21 |
1,000 with 5% Waste % Add-on = 1,050 LF |
|
Code |
Description |
Quantity |
|---|---|---|
|
CPIPE |
Pipe Crew |
1 |
|
Days |
3 |
You should end up with the similar results:
Congratulations, you have completed this exercise!