Log into the InEight Progress mobile application.
Select a project from the Projects home page.
Tap on the Add
button to create a plan from scratch.
Choose a date for the daily plan.
Give a description in the Enter Plan Description field.
Enter a location in the Enter Location field.
Select a shift from the Job Shift menu.
Select an Approver.
Maximum of 2 selections. Usually an engineer and superintendent
Select an Executer.
Only one selection. Usually a foreman
Select Work Plan/Package.
Select a work plan or package for the daily plan and tap Back.
Tap Add to create a plan.
Tap the Add button in the Safety section of Tool box talks to add project safety concerns and mitigation.
Tap the Quality tab and add a quality concern and mitigation.
Tap Done to add the Tool Box Talk items to the Overview screen.
Tap on the Time sheet tab.
Tap on the Add button.
If not already selected, tap the Task button at the top.
Select a task (i.e. 1005 – Erect Steel Light).
You can perform a search to find the task or scroll through the list
Tap on the Employee tab, then tap select the employees you want to add.
Tap on the Equipment tab, then select the equipment you want to add.
Tap Done.
You will see the task, employee, and equipment appear on the Time sheet tab
Add employee time by tapping on the empty box next to an employee name.
Check the box for “Apply hours to all employees for the task” and then select Done to apply these hours to all of the employees selected for this daily plan.
You can choose between straight time (ST), over time (OT), and double time (DT). Other premiums can be set within the project settings from the Progress web application.
Add equipment time by tapping on the empty box next to a piece of equipment.
Check the box for “Apply hours to all equipment for the task” and then select Done to apply these hours to all of the equipment chosen for your daily plan.
Tap on the Quantities tab.
This opens the components section of each task
You can also input the planned quantity
Select your task (i.e. 1005 – Erect Steel Light).
Tap the Add Components
button.
Then, tap on the Search All tab.
In the search bar, type in a keyword and select your components.
Tap Done to add the component to the quantities.
Check the check boxes in the Complete column as needed for your components or their broken down steps.
Tap on the Notes/Issues tab.
Tap on the Add button and select Note to add any project notes.
Tap on the Tag
icon to add any tags.
icon to take a photo, make markups, or add text.Tap on the Productivity tab and review your daily plan.
Review the Planned Quantity, Planned MHRs, and Gain/Loss.
Tap the double arrows to flip between MHRs per Qty and Qty per MHRs
Tap on the Submit button.
Once you tap Submit, a window appears asking if you are sure that you want to move the plan into execution
Tap Submit again.
The application will automatically sync after submitting a plan to execution
Once you click submit, you will no longer be able to edit your plan. The only way to edit is to communicate with the engineer or superintendent to reject the plan or have them edit for you.