Review 

  1. Where can you enter schedule dates for your cost items?

    1. Cost item details

    2. Task details data block

    3. Schedule data block

    4. On the Schedule tab

    5. On the Schedule slide out panel

  2. Using the Control Import feature, you can import which of the following types of data?

    1. Tasks

    2. Current Estimate

    3. Schedule

    4. Cost Categories

    5. All of the above

  3. When importing a Primavera schedule, the Schedule ID in Control must match the
    _______ in the XER file.

    1. Import ID

    2. Current Estimate ID

    3. Task Details ID

    4. Activity ID

    5. Start Date ID

  4. When using the Define project schedule: Schedule data source feature, which option allows you to export a Primavera formatted file to eventually be used to import directly into Primavera?

    1. Manual entry file

    2. XER file type

    3. Activity ID file type

    4. Task Details file type

    5. Schedule file type

Summary 

As a result of this lesson, you can:

  • Navigate to the Schedule data block

  • Edit schedule data inside the CBS

  • Edit schedule data using Excel import

  • Integrate planning activities

  • Schedule using Primavera