From the Project home page, select the 1st Level drop-down menu.
Select Master Data Libraries.
Select Account Codes.
All the account codes appear on your screen in a hierarchy format
Select the Staging tab.
Click the check box next to any of the existing account codes.
Click the Add Account Code button.
This creates a new account code with the code you selected as the parent
In the Account code details slide out panel, the following can be assigned:
Item |
Function |
---|---|
Parent Account Code |
Account Code with lower level “child” account codes below it. |
Account Code |
The alpha numeric sequence assigned as the code. |
Description |
Description detailing the account code’s scope. |
Currency |
The currency assigned to the account code. |
UoM Primary |
The primary unit of measure for the account code. |
UoM Secondary |
The secondary unit of measure for the account code. |
Auto Quantity Primary/Secondary |
Automatically roll up cost item quantities if the cost items and this account code have the same primary/secondary UoMs. It can also be set on a project specific basis. |
Parent Roll Up Behavior |
Controls whether primary or secondary quantities of account code roll up to the parent account code’s primary or secondary quantity. |
Account Code Tag 1-20 |
Tags that can be associated to account codes to enable them to be categorized. |
User Defined Field 1-10 |
Optional open-text fields you can use to add information related to the account code. |
The asterisk (*) at the beginning of a tile indicates it is a required field and it must be populated before the code will be created.
Fill in the information below:
When you have filled out all the information, click Stage to send the new account code to staging area.
The new account code now exists in the Account Code Structure on the Staging tab
The new account code will not be available for use within projects until it is published
If you have the permissions to publish account codes, check the box for the account code you created..
Click the Publish button in the top-right corner of the page.